This is more of a placeholder right now as I'm waiting on the Anderson connectors to get here this week to start this.
From what I can tell the project will take :
1. Anderson connector to plug into the mowers factory charge port : ordered
2. Wire to go from the Sungold tp6048 to the mower : check - Ive got 25 feet of 2 gauge welding cable
3. Upgrading the internal charge port cable that runs from the charge port to the batteries and its fuse.
(Current wire size unknown but I know it has a 20 amp fuse for the charge port and a 150 amp fuse for the rest of the mower)
(I may use some of the 2 gauge welding cable to upgrade this. Still will need a fuse of some kind.)
- Ordered
4. Breaker box and 100 amp dc breaker which will be mounted before the Sungold tp6048. - ordered
5. A Victron smart shunt since the solar assistant for the sungold unit running on a orange pi 3 lts is compatible with it and can keep up with the SOC on the mower.
That's all I can think of at the moment. Suggestions as to anything I'm not thinking of?
From what I can tell the project will take :
1. Anderson connector to plug into the mowers factory charge port : ordered
2. Wire to go from the Sungold tp6048 to the mower : check - Ive got 25 feet of 2 gauge welding cable
3. Upgrading the internal charge port cable that runs from the charge port to the batteries and its fuse.
(Current wire size unknown but I know it has a 20 amp fuse for the charge port and a 150 amp fuse for the rest of the mower)
(I may use some of the 2 gauge welding cable to upgrade this. Still will need a fuse of some kind.)
- Ordered
4. Breaker box and 100 amp dc breaker which will be mounted before the Sungold tp6048. - ordered
5. A Victron smart shunt since the solar assistant for the sungold unit running on a orange pi 3 lts is compatible with it and can keep up with the SOC on the mower.
That's all I can think of at the moment. Suggestions as to anything I'm not thinking of?
Last edited: