Well top marks to Western Power South Wales, UK ?. I called them up last Thursday and raised a G99 query "which form do I fill in for a 6kW inverter with 15kWh battery and no grid export ?". The engineer rang me back next day and sent me the relevant form (A1-1) which I completed and returned over the weekend. Also had to attach a schematic of my install and inverter certificates for G99 and G100 compliance. A few queries back from them on Tuesday which I fixed same day and I got my G99 approval at 8:45am this (Thursday) morning ! Chuffed to bits . That's a 3 working day turn around from their side start to finish ! Fantastic service ! I thought I'd be on the hook for a 12week wait !
Lessons learnt in my case
(1) Call up the DNO as soon as possible and ask them what forms need to be completed. Don't try and figure it out yourself ! I am still not clear how I managed to fast track with A1-1 and I think the forms needed by each DNO are specific to their internal process. You'll never work it out from websites and the requirements seem a little random from the forums for each DNO. Talk to a human !
(2) Draw a schematic of your install (make sure it matches the inverter install manual) and download copies of all the inverter certificates seems key to a fast turn around. They will want pdf copies.
(3) No export in my case meant it was eligible for fast track. My approval limits export to no more than 3.68kW (16A) which is fine for me, I want to export 0kW! But timescales might be different if you want to exceed 16A.
I did apply and was granted 5kW system. Then had a 2kW system installed but I want to add a 3.7 system with a battery.Did you apply via UK Network Power? If you did how long did it take for you to get a response? Do you need to do a G99? An inverter of 3.68kW can be installed and a G98 completed after installation. Maximum export should be limited to 3.68kW using a G100 device. The only reason you would a G99 is if you intended to export more than that or don't have a G100 compliant inverter / device.
I spoke with Scottish Power Networks yesterday and they stated that as my inverter (Solis 8Kw 5G looking after 10Kw array) was G99 certified and will limit export to 3.68Kw only a retrospective G98 would be required.The simpler G98 procedure (i.e. install first then inform the DNO) only applies to devices that can export a max of 16A - i.e. 3680W at the nominal 230V.
As your inverter (RHI-6K-48ES-5G) has the _capability_ of exporting more than 16A you will need to go through a G99 approval, which requires acceptance from the DNO before installation. I'd recommend you do that before buying the inverter as the DNO could say they require £££ to upgrade the network before such a device is attached to it.
As far as I'm aware, the fact that you _could_ limit the export power to a value lower than 3680W on that inverter does not exempt from G99 approval as the DNO doesn't have control over what you set your inverter to actually do.
I have the G100 certificate from Solis for my inverter, just confused about Scottish Powers statementNow I thought that an inverter that was rated 8kw that limited export to 3.68kw would need to be a G100 compliant, and therefore a G100 application.
Yes, that's not how I read the requirements, but maybe each DNO has their own interpretation and/or flexibility. I thought the whole point about the G99 application is the DNO would tell you the maximum you could export. And thereafter, you can go and install an inverter that is G99 and G100 compliant (and installed according to the regs - e.g. wired export limit connection + configured to cut-off if grid export connection goes down) - with the added condition that the DNO reserves the right to come and observe the commissioning if they want to. But I stand corrected if that's not the official case.... just confused about Scottish Powers statement
Can you explain what you mean here... if the inverter is connected to your supply, which is connected to the grid then DNO notification or approval is required, depending on inverter's output power.... This would be assuming utility power could be used for battery charging, therefore never AC coupled...