I understand this is an old Post how did you go ?
As i looking at doing something similar possibly
I have a sunny island in Si8.0 setup in battery back up with Grid Connection (which has solar on the grid connect side )
Installed this about few years ago and never had time to finish off setting it up it has saved me money but i know i could save a ton by configuring it up properly
A2 is my Grid connect Input which has my PV Solar input on that side as well so when i have too much solar during the day it just exports back to the grid otherwise it just goes through the SI and if it needs more than 4kw in high demand hours it takes from the batteries as the A2 max current set at 4kw as i have approx 10kw solar on the roof
A1 is my Load side of The Sunny Island that feeds my power to the house.
Im finding that i generate more pv than i use during the day but at night i wasting money as im using grid power and i have over 50kw of gel vrla batteries (25kw of safe discharge for maintaning healthy batteries).
So i wanting to work out the best alternative as this sounds ok what you mentioned above
Im looking at setting it up so when my solar input drops in the evening that the Grid A2 disconnects and then reconnects in the morning when my solar starts back up or if the batterys fall below 50% but only want to start charging the batteries when im generating more solar than im using otherwise im paying high cost to charge the batteries from the grid power not solar for free as my A2 grid input is set to 4kw
Maybe my other option is setting up the Solar PV on A1 load side and installl a PV contactor to disconnect Solar if the grid network goes down so not to feed back into the grid which is easy. But not sure of the programming parameters to set the Pv to feed back through A2 and paramters for a2 to kick in when batterie levels fall below 40% and when to shut off etc. I guess this would be the best setup. As i still want to export solar to the grid during the day and not have my solar inverters shut down when theres excess solar on A1 load side even though the energy provider gives little back, its better than nothing and helps offset the feed in cost a bit.
any advice welcomed or paramters settings i need to look at etc