NVCYberPro
New Member
- Joined
- Dec 15, 2022
- Messages
- 80
Hello,
I am planning my off grid solar system, I am currently on grid and intend to pull the plug. I will need to do this is steps so my plan is as follows.
I have a 6 circuit Generator Transfer switch installed next to my main panel (200 Amp) in my laundry room. I want to extend the wiring for the Emergency Generator input for those 6 circuits downstairs in the basement where my Inverters and batteries will be mounted. This run is an estimated 35 feet and I have been calculating 50 feet for safety.
Since I plan to pull the plug and go off grid - I want to size the wiring to the basement to handle the final load, not just run the 50 amps from the generator.
The plan is to use 2 LV6548's or EG4's or similar devices in parallel to provide 120/120 split phase. All the data I have indicates I would use 4 AWG from each inverter to a sub panel mounted in the basement, those units only allow for a 4 AWG wire. If I am doing my calculations correctly I would need to run 1 AWG or 1/0 AWG from these units to the main panel upstairs. Is that correct and if so, how do I do that and convert from the 4 AWG (Ground, Neutral, L1 & L2) from the inverters to 1 AWG or 1/0 AWG run upstairs.
Again the first step would be to wire these to the input of the Generator transfer switch. When the system is 100% built out we would disconnect from the utility and connect the output of the basement inverters into the main panel. I would like to run the correct wire upfront instead of rewiring later.
Thank you
I am planning my off grid solar system, I am currently on grid and intend to pull the plug. I will need to do this is steps so my plan is as follows.
I have a 6 circuit Generator Transfer switch installed next to my main panel (200 Amp) in my laundry room. I want to extend the wiring for the Emergency Generator input for those 6 circuits downstairs in the basement where my Inverters and batteries will be mounted. This run is an estimated 35 feet and I have been calculating 50 feet for safety.
Since I plan to pull the plug and go off grid - I want to size the wiring to the basement to handle the final load, not just run the 50 amps from the generator.
The plan is to use 2 LV6548's or EG4's or similar devices in parallel to provide 120/120 split phase. All the data I have indicates I would use 4 AWG from each inverter to a sub panel mounted in the basement, those units only allow for a 4 AWG wire. If I am doing my calculations correctly I would need to run 1 AWG or 1/0 AWG from these units to the main panel upstairs. Is that correct and if so, how do I do that and convert from the 4 AWG (Ground, Neutral, L1 & L2) from the inverters to 1 AWG or 1/0 AWG run upstairs.
Again the first step would be to wire these to the input of the Generator transfer switch. When the system is 100% built out we would disconnect from the utility and connect the output of the basement inverters into the main panel. I would like to run the correct wire upfront instead of rewiring later.
Thank you